Feb. 4, 2019

Print | PDF

Washroom upgrades at 202 Regina St. will begin on

Feb. 19 until March 15, 2019. There will only be two washrooms offline and six will remain open at all times.

Work involved is as follows:

  • Counter and sink replacements.
  • New faucets and soap dispensers.
  • Painting.

Upgrade Schedule

As per the schedule below, the contractors will close each bathroom, demolish, install the new finishes and then re-open. 

  • Feb. 19 to 22: R120 and R110A
  • Feb. 25 to March 1: R121A and R111A
  • March 4 to 8: R265 and R273
  • March 11 to 15: R267 and R272
×